Precedent applications (4)

  • preliminary_platunknownDryden Acres
    Auto-extracted

    Filed: ? · Decided: ?

    Preliminary Plat application for Dryden Acres subdivision involving Lots 1-3, Block 1, and Outlot A, submitted by Deb & Randy Dryden.

  • preliminary_platunknownDryden Acres
    Auto-extracted

    Filed: ? · Decided: ?

    Request for approval of a 4-lot Preliminary Plat for Dryden Acres at 6660 and 6700 Viking Blvd.

  • preliminary_platunknownDryden Acres
    Auto-extracted

    Filed: ? · Decided: ?

    Randy and Deb Dryden request approval of Preliminary Plat to subdivide 3 existing lots into 4 parcels with street right-of-way dedication and cul-de-sac establishment.

  • preliminary_platunknownDryden Acres
    Auto-extracted

    Filed: ? · Decided: ?

    Request for approval of a 4-lot Preliminary Plat for Dryden Acres at 6660 and 6700 Viking Blvd.

Findings on this issue (0)

  • No findings recorded on this issue yet.

Conditions imposed on this issue (80)

otherAuto-extracted

The driveway surfacing, clearance, and turning radius must be designed to accommodate emergency fire vehicles.

Petersen Acres
otherAuto-extracted

The address of the flag lot must be clearly visible from the public street.

Petersen Acres
otherAuto-extracted

The project must have a stormwater maintenance agreement.

Petersen Acres
otherAuto-extracted

Do not build any structures within the flagpole portion of the lot or within easements.

Petersen Acres
otherAuto-extracted

Design and maintain the access from 205th Avenue NW to accommodate emergency vehicles.

Petersen Acres
otherAuto-extracted

Pay all costs associated with processing this request.

Petersen Acres
otherAuto-extracted

Outlot A is not buildable and must either be combined with Lot 1, Block 1, or transferred to the adjacent property owner to the north with the outlot area combined with the off-site property at final plat recording.

Petersen Acres
otherAuto-extracted

Complete all items required by the Development Agreement before the financial security can be released.

Petersen Acres
otherAuto-extracted

The CUP issued July 9, 2024 is revoked, and the City Attorney must include the revocation in the Developer’s Agreement or other recording document.

Petersen Acres
otherAuto-extracted

All public infrastructure (including water, sanitary sewer, stormwater, and roads) must be dedicated or located within a drainage and utility easement.

Petersen Acres
otherAuto-extracted

Construct improvements in substantial conformance with the Site Plans as revised to meet the Staff Memos’ requirements.

Petersen Acres
otherAuto-extracted

If updated site plans require changes to lot lines or easements, those changes must be incorporated into the Final Plat submitted by the developer.

Petersen Acres
otherAuto-extracted

If there is a conflict between the site plans and the resolution, the resolution controls unless modified by a final plat resolution.

Petersen Acres
otherAuto-extracted

The timing of construction of infrastructure improvements is subject to conditions in a Developer’s Agreement between the City and the developer.

Petersen Acres
otherAuto-extracted

Provide financial security (form approved by City Attorney and amount approved by City Engineer) before release of the final plat for recording, with the amount specified in the Developer’s Agreement.

Petersen Acres
otherAuto-extracted

The Development Agreement approval is subject to review and approval by the City Attorney, City Planner, and City Engineer.

Petersen Acres
otherAuto-extracted

The Developer must, at its sole expense, construct the City improvements on and off the plat in accordance with the Approved Plans on file with the Interim City Administrator.

Petersen Acres
otherAuto-extracted

The numbered lots are restricted to single-family residential use as shown on the plat.

Petersen Acres
otherAuto-extracted

Before recording, a soil borings report must be submitted for review.

Petersen Acres
otherAuto-extracted

If updated Site Plans require revisions to lot lines or easements, the developer must incorporate those revisions into the Final Plat and revise Site Plans and the Final Plat as necessary, including possible changes or removal of lots, outlots, easements, or right of way.

Petersen Acres
otherAuto-extracted

When revising the plans, include a revision date on the plan set and rename the plans from Petersen Court to a different name because Petersen Court is not the road name.

Petersen Acres
otherAuto-extracted

Place City-approved signage along lot lines or corners next to storm ponds, wetlands, and conservation areas.

Petersen Acres
otherAuto-extracted

If updated Site Plans require changes to lot lines or easements, incorporate those changes into the Final Plat; revise plans/plat as needed (including potential removal/changes of lots/outlots/easements/right-of-way), and provide any required off-site easement document to the City for approval before recording.

Petersen Acres
otherAuto-extracted

The driveway surfacing, clearance, and radius must be designed to accommodate emergency fire vehicles.

Petersen Acres
otherAuto-extracted

The flag lot address must be clearly visible from the public street.

Petersen Acres
otherAuto-extracted

No structures may be built within the flagpole portion of the lot or within easements.

Petersen Acres
otherAuto-extracted

The access from 205th Avenue NW must be designed and maintained to accommodate emergency vehicles.

Petersen Acres
otherAuto-extracted

The City Engineer may require the driveway to be paved or other drainage control measures to prevent runoff onto neighboring properties.

Petersen Acres
otherAuto-extracted

The conditional use permit may be subject to revocation if the approved conditional use is not exercised within one year of approval unless a written extension request is submitted at least 30 days before the deadline.

Petersen Acres
otherAuto-extracted

The applicants must pay all costs associated with processing this request.

Petersen Acres
otherAuto-extracted

Outlot A is not buildable and must be combined with Lot 1, Block 1 or transferred to the adjacent northern property owner, and if transferred it must be combined with the off-site property when the final plat is recorded.

Petersen Acres
otherAuto-extracted

Provide a 20-foot-wide trail easement on the south side of 205th Avenue NW.

Petersen Acres
otherAuto-extracted

All public infrastructure (including water, sanitary sewer, stormwater, and roads) must be dedicated or located within a drainage and utility easement.

Petersen Acres
otherAuto-extracted

Improvements must be constructed in substantial conformance with the Site Plans as revised to meet the Staff Memos’ requirements.

Petersen Acres
otherAuto-extracted

If compliance results in changes/removal of lots, outlots, easements, or right-of-way, the developer must revise the site plans and final plat as necessary to conform.

Petersen Acres
otherAuto-extracted

If Site Plans conflict with this resolution, the resolution controls unless modified by a final plat resolution.

Petersen Acres
otherAuto-extracted

Construction timing for infrastructure improvements is subject to conditions in a Developer’s Agreement between the City and Developer.

Petersen Acres
otherAuto-extracted

Before the final plat is released for recording, the developer must provide financial security in a form approved by the City Attorney and amount approved by the City Engineer, with the Developer’s Agreement specifying the amount.

Petersen Acres
otherAuto-extracted

Revoke the Conditional Use Permit granted by Resolution #2024-71, and have the City Attorney include the revocation in the Developer’s Agreement or other recorded document.

Petersen Acres
otherAuto-extracted

Comply with and incorporate all comments in the City Engineer memo dated February 19, 2025 and the Collaborative Planning memo dated January 23, 2025.

Petersen Acres
otherAuto-extracted

Before starting subdivision construction, the developer must enter into a development agreement with the City.

Petersen Acres
otherAuto-extracted

If the Approved Plans conflict with this Agreement, the written terms of the Agreement control, and improvements must be installed by October 31, 2025 unless the City Engineer allows a later date.

Petersen Acres
otherAuto-extracted

The Developer and Landowners may not alter lot configuration and may build only one single-family dwelling per numbered lot unless the City later agrees to changes.

Petersen Acres
otherAuto-extracted

The final plat approval is conditioned on compliance with the attached Findings of Fact and Record of Decision (Exhibit A).

Petersen Acres
otherAuto-extracted

Provide a 20-foot-wide trail easement on the south side of 205th Avenue NW, have it reviewed by the City Attorney, and record it with the final plat and Development Agreement.

Petersen Acres
otherAuto-extracted

Comply with all comments in the City Engineer memo (Hakanson Anderson, August 19, 2024) and the City Planner memo (Collaborative Planning, August 21, 2024), which are incorporated as conditions.

Petersen Acres
otherAuto-extracted

The development must comply with the City Engineer and City Planner comment memos.

Petersen Acres
otherAuto-extracted

Provide a 20-foot-wide trail easement on the south side of 205th Avenue NW, submit it for City Attorney review, and record it at the same time as the final plat.

Petersen Acres
otherAuto-extracted

The driveway surfacing, clearance, and turning radius must be designed to accommodate emergency fire vehicles.

Petersen Acres
otherAuto-extracted

The address of the flag lot must be clearly visible from the public street.

Petersen Acres
otherAuto-extracted

The conditional use permit may be subject to revocation if the use or operation is discontinued for one year.

Petersen Acres
otherAuto-extracted

The applicants must pay all costs associated with processing this request.

Petersen Acres
otherAuto-extracted

A conditional use permit for the flag lot must be obtained before final plat approval, or the plat must be reconfigured to eliminate the flag lot.

Petersen Acres
otherAuto-extracted

Outlot A must not be buildable and must either be combined with Lot 1, Block 1 or transferred to the adjacent north property owner, with any transferred area combined with the off-site property at final plat recording.

Petersen Acres
otherAuto-extracted

Before the financial security for Petersen Acres can be released, items required by the Development Agreement must be completed.

Petersen Acres
otherAuto-extracted

Improvements must be constructed in substantial conformance with the site plans as revised to meet the Staff Memos’ requirements.

Petersen Acres
otherAuto-extracted

Provide a title commitment for the City Attorney’s review before the final plat is released for recording.

Petersen Acres
otherAuto-extracted

The preliminary plat approval is subject to the Findings of Fact and Record of Decision attached as Exhibit A.

Petersen Acres
otherAuto-extracted

Dedicate all public infrastructure or place it within a drainage and utility easement.

Petersen Acres
otherAuto-extracted

Before starting subdivision construction, the developer must enter into a development agreement with the City.

Petersen Acres
otherAuto-extracted

Any approval of the Petersen Acres Development Agreement would be subject to the City Attorney approving the final agreement.

Petersen Acres
otherAuto-extracted

The Developer and Landowners must grant the City and its representatives a right of entry to the plat to perform work and inspections and to take corrective actions deemed necessary under the Agreement.

Petersen Acres
otherAuto-extracted

Before recording, the final plat must be revised according to the comment memos.

Petersen Acres
otherAuto-extracted

Before recording, project specifications must be prepared and submitted to the City Engineer.

Petersen Acres
otherAuto-extracted

A 20-foot-wide trail easement must be provided on the south side of 205th Avenue NW, reviewed by the City Attorney, and recorded with the final plat and Development Agreement.

Petersen Acres
otherAuto-extracted

All comments in the City Engineer memo from Hakanson Anderson dated October 2, 2024 and the memo from Collaborative Planning dated October 2, 2024 are incorporated as conditions.

Petersen Acres
otherAuto-extracted

The final plat may be approved, but it cannot be released for recording until the soil borings and specifications documents and the wetland replacement plan review items are completed.

Petersen Acres
otherAuto-extracted

Place City-approved signage along lot lines or corners next to storm ponds, wetlands, and conservation areas.

Petersen Acres
otherAuto-extracted

The applicant must provide the required park dedication for this plat, with the amount calculated when the development agreement is executed.

Petersen Acres
otherAuto-extracted

The City Council may hold a public hearing to revoke the conditional use permit if the use or operation is discontinued for one year.

Petersen Acres
otherAuto-extracted

Avoid violations, discontinuation for one year, or failure to exercise the conditional use within one year (unless a timely written request is submitted), to prevent potential revocation hearing by the City Council.

Petersen Acres
otherAuto-extracted

Have the plans reviewed by the City’s septic consultant before final plat approval.

Petersen Acres
otherAuto-extracted

No structures may be built within the flagpole portion of the lot or within easements.

Petersen Acres
otherAuto-extracted

The access from 205th Avenue NW must be designed and maintained to accommodate emergency vehicles.

Petersen Acres
otherAuto-extracted

The driveway may be required by the City Engineer to be paved or to include other drainage controls to prevent runoff onto neighboring properties.

Petersen Acres
otherAuto-extracted

The conditional use permit may be subject to revocation if permit conditions are violated.

Petersen Acres
otherAuto-extracted

The City Council may hold a public hearing to revoke the conditional use permit if the approved conditional use is not exercised within one year of approval unless a written request is submitted at least 30 days prior to the deadline.

Petersen Acres
otherAuto-extracted

Outlot A is not buildable and must either be combined with Lot 1, Block 1 or transferred to the adjacent property owner to the north (and if transferred, combined with that off-site property at final plat recording).

Petersen Acres
otherAuto-extracted

Complete the items required by the Development Agreement before the City releases the financial security for Petersen Acres.

Petersen Acres
otherAuto-extracted

A 20-foot-wide trail easement is required on the south side of 205th Avenue NW.

Petersen Acres